The View
Tuesday, March 29, 2016
Roof
Half of the roof trusses are getting swung.
Monday, March 28, 2016
Update
Roof truss sections are built in preparation to swing Tuesday.
Tuesday, March 15, 2016
Update
All 5th floor exterior walls are up. We are working on building party walls now.
Thursday, March 10, 2016
Elevator and 5th floor
The elevator is nearing the top.
5th floor exterior walls are being tipped up.
A few views from the 5th floor.
Friday, March 4, 2016
Update
The elevator shaft is up to the 5th floor and we are pulling the hydro out of the shaft.