Saturday, February 27, 2016

Update

All of the 5hh floor trusses are set. The elevator shaft is up to the 4th floor. 






Thursday, February 25, 2016

5th floor

Half of the floor trusses for 5th are set. 



The elevator shaft is starting up again. 






Friday, February 19, 2016

Update

Steel stairs are being installed. 




4th floor - half of the unit walls are built. The rest are getting prepared to be build. The first half of 5th floor trusses will be delivered today. We will swing the first half Tuesday next week. 



Both Lake Monona and Lake Mendota can be see from the 4th floor. 







Wednesday, February 17, 2016

4th floor

The hallway and unit separation walls are built. We are now starting the interior unit walls. 






Friday, February 12, 2016

Update

All 4th floor exterior walls are set and demising walls are being built. 




Thursday, February 11, 2016

4th Floor Walls

Half of 4th floor exterior walls are up and the remainder will be tipped up today.







Monday, February 8, 2016

Update

4th floor exterior walls are built and getting ready to stand tomorrow. 



Stairs are built from 3rd to 4th floor. 


A view towards downtown.