Thursday, August 11, 2016

Retaining Wall

The first half of the retaining wall is poured and forms removed. 




Wednesday, June 22, 2016

Steel

The structure steel at the corner of Jupiter and North Star is being erected. 








Tuesday, June 21, 2016

Update

1st floor - ceiling drywall grid is being installed. 



2nd floor rough mechanicals are finishing up. 



3rd floor insulation is wrapping up. 




4th floor drywall is being taped. 




5th floor hard floors are installed and Millwork is going in. 



















Wednesday, June 8, 2016

Tuesday, June 7, 2016

Monday, June 6, 2016

5th floor

10 of the 17 units are painted out. Ready for flooring, accents and cabinets. 







Friday, June 3, 2016

Wednesday, June 1, 2016

Update

Sound mat is being laid today in preparation of lightweight floors tomorrow. 






Wednesday, May 18, 2016

Thursday, May 12, 2016

Thursday, May 5, 2016

Wednesday, April 27, 2016

5th floor

Pre-rock is complete and tubs are being set. HVAC is pushing along and the electricians are following. 




Monday, April 18, 2016

Update

The roof is about 70% complete. We are starting to load drywall for pre-rock in the dried in areas. 


Tuesday, April 12, 2016