Thursday, November 12, 2015

Update


The lower level parking garage is poured.


1st floor steel studs are being installed.


2nd floor walls are being built


A View from the 2nd floor towards downtown.

Monday, September 28, 2015

Update

Upper level parking garage has been poured. 


Exterior brick veneer is being installed. 



Friday, August 28, 2015

Project Update

The last couple foundation walls are being prepped to pour. 



The CUM is being installed on 1/3 of the first floor exterior walls. 







Friday, July 24, 2015

Lower Level Pre-Cast

The pre-cast over the lower level parking garage is set. The masons and concrete guys are getting the next layer of the foundation started.


Wednesday, July 15, 2015

Pre-cast

The columns and beams are going in at the View. Today we will start setting the plank. 








Monday, July 6, 2015

Foundation

The lower parking garage is nearly complete. Just pouring the last of the column pads. About half of the garage walls have been painted. 






Tuesday, June 30, 2015

Lower foundation

We are nearing completion of the lower foundation. The last section of wall will be poured Thursday with pre-cast starting 7/9. The bearing block walls are also being installed. 












Tuesday, June 23, 2015

Update

Most of the foundation has been back filled. We are prepping the footings by the overhead garage door and forming more foundation walls. 







Monday, May 18, 2015

Foundation

About half of the footings have been poured. The elevator shaft is getting ready to be poured tomorrow. 

Rebar is going in for the foundation walls. 










Wednesday, May 13, 2015

Footings

The footings are starting to get formed and should start pouring concrete towards the end of the week. 


Wednesday, May 6, 2015

Wednesday, April 22, 2015