Thursday, August 11, 2016

Retaining Wall

The first half of the retaining wall is poured and forms removed. 




Wednesday, June 22, 2016

Steel

The structure steel at the corner of Jupiter and North Star is being erected. 








Tuesday, June 21, 2016

Update

1st floor - ceiling drywall grid is being installed. 



2nd floor rough mechanicals are finishing up. 



3rd floor insulation is wrapping up. 




4th floor drywall is being taped. 




5th floor hard floors are installed and Millwork is going in. 



















Wednesday, June 8, 2016

Tuesday, June 7, 2016

Monday, June 6, 2016

5th floor

10 of the 17 units are painted out. Ready for flooring, accents and cabinets. 







Friday, June 3, 2016